46A Village Farm Ind. Estate
Pyle, Bridgend, CF33 6BP
T 01656 745838
F 01656 740596
info@jmccarthy.biz
ISO 9001-14001-45001 combined

Cowbridge & Llanblethian Flood Alleviation Scheme

The scheme was designed to provide a measure of protection for residents and commercial properties, considered to be at risk from a 1 in 100 year flood event. It involved the construction of a shallow earth embankment dam and a 50m long reinforced concrete flood control structure on the flood plain of the River Thaw and divert flood flows onto the natural floodplain away from Cowbridge and Llanblethian.

The dam was constructed using 18,000m3 of Class 2c material which was sourced from quarry waste and processed to meet the specification. All site excavated material was reused with the end result that no material was taken to landfill.

To facilitate construction of the structure, a 100m long river diversion was required. This was constructed out of blockstone to provide a natural habitat for fish.

Scheme Features

Carillion and Atkins worked closely to develop the sequence of construction activities and gain planning consent. This involved planning the haulage route, access and local improvements. Carillion developed solutions to construct protection slabs and temporary bridges to eliminate the requirement for statutory undertaker diversions around the site. The dam came under the control of the Reservoir Act and all construction materials and methods were subject to independent approval.

Good community liaison was of paramount importance. A newsletter was published throughout the scheme together with press releases that kept the public informed. The site team arranged regular site visits and presentations with the Local Authority - Vale of Glamorgan Council and the local Rotary Club. Carillion worked closely with the EA, CADW and CCW on this environmentally sensitive scheme. Particular care was taken as the scheme was located close to Cowbridge Comprehensive School.

The environmental impact of the scheme was carefully considered and many features were constructed which have a positive effect on wildlife such as the creation of ponds and scrapes to attract water birds and insects and the development of an environmental area to encourage native wild flowers and plant life. Carillion is committed to sustainable construction and as well as sourcing secondary aggregates the team amended the design of the slopes to take any surplus topsoil. The scheme had positive KPI scores and was nominated for a Wales ICE award.

Cowbridge and Llanblethian FAS


Value Engineering

  • Increaed thickness of Topsoil
  • Reuse of existing river channel material
  • Reuse of as dug material
  • Removal of requirement for wheel wash
  • Temp bridge to avoid diversion
  • Protection slab to avoid diversion

Sustainability

  • All material excavated reused on site by riddling or processing - zero taken to tip
  • All timber sleepers from recycled source
  • All fill secondary aggregrate - quarry waste

Environmental

  • Noise and dust controlled working adjacent to secondary school - restricted hours of work
  • Runoff controlled by using excavation and three stilling ponds
  • Fish rescue for river diversion
  • Silt control for in river working and diversions - liaison with EA - Env. Man
  • Environmental enhancements constructed with EA biodiversity team

Supply Chain

  • Carillion - Main Contractor
  • J McCarthy - earthworks
  • J Hasset - Formwork
  • Hartley - Penstock
  • Salix - Matting and environmental planting
  • Afan - Landscaping
  • Cleddwyn Gardener - Fencing

Early Contractor Involvement

  • Built up PAR report which includes construction methods, VE, costs and risks
  • Liaised with Statutory Authorities

Risks

  • River diversion - contamination and silt
  • Working hours reducing construction period
  • Working adjacent to school

Archaeology

  • Enabling works were undertaken to investigate site

Involvement of other consultants etc

  • CADW
  • CCW
  • Additional EA - Biodiversity

Project Successes

  • Within PAR budget - few risks realised through careful planning
  • Nominated for ICE award
  • Successful KPI scores
  • Signed off by Panel engineer with no hitches
  • River Diversion viewed as successful and sustainable

Partnering

  • Framework with Atkins, EC Harris

Whole Life Costs / Maintenance

Unusual engineering techniques

Client Environment Agency
Contact Mr Scott Squires
Value Award £ 1.4m
Outturn £ 1.5m
Role Main Contractor
Principal Designer Atkins Tel: 01792 641172
Contact: Mr Huw Richards
Form of Contract NEC Option C
Contract Period 26 weeks
Dates May 2006 to Nov 2006

Project Photos