NPT Recycling

Project consisted of the construction of a reinforced concrete slab for dust extraction apparatus. This would remove dust from within the recycling operation within the adjacent building.

McCarthy's Role

Principal Contractor carrying out all management and works required for the completion of the dust extraction slab: -

  • Site set-up including traffic management
  • Saw cut and break out existing reinforced concrete slab
  • Erect shutters, reinforcement and screed rails
  • Pour and finish reinforced concrete slab
  • Remove shutters
  • Install precast concrete bollards to outer corners of completed slab
  • Complete kerbline to new slab edge

Client Neath Port Talbot Waste Management
Principal Contractor McCarthy's
Principal Designer James & Nicholas
Contract Period 2 weeks