The scheme was designed to provide a measure of protection for residents and commercial properties, considered to be at risk from a 1 in 100 year flood event. It involved the construction of a shallow earth embankment dam and a 50m long reinforced concrete flood control structure on the flood plain of the River Thaw and divert flood flows onto the natural floodplain away from Cowbridge and Llanblethian.
The dam was constructed using 18,000m3 of Class 2c material which was sourced from quarry waste and processed to meet the specification. All site excavated material was reused with the end result that no material was taken to landfill.
To facilitate construction of the structure, a 100m long river diversion was required. This was constructed out of blockstone to provide a natural habitat for fish.
Carillion and Atkins worked closely to develop the sequence of construction activities and gain planning consent. This involved planning the haulage route, access and local improvements. Carillion developed solutions to construct protection slabs and temporary bridges to eliminate the requirement for statutory undertaker diversions around the site. The dam came under the control of the Reservoir Act and all construction materials and methods were subject to independent approval.
Good community liaison was of paramount importance. A newsletter was published throughout the scheme together with press releases that kept the public informed. The site team arranged regular site visits and presentations with the Local Authority - Vale of Glamorgan Council and the local Rotary Club. Carillion worked closely with the EA, CADW and CCW on this environmentally sensitive scheme. Particular care was taken as the scheme was located close to Cowbridge Comprehensive School.
The environmental impact of the scheme was carefully considered and many features were constructed which have a positive effect on wildlife such as the creation of ponds and scrapes to attract water birds and insects and the development of an environmental area to encourage native wild flowers and plant life. Carillion is committed to sustainable construction and as well as sourcing secondary aggregates the team amended the design of the slopes to take any surplus topsoil. The scheme had positive KPI scores and was nominated for a Wales ICE award.
Value Engineering
|
Sustainability
|
Environmental
|
Supply Chain
|
Early Contractor Involvement
|
Risks
|
Archaeology
|
Involvement of other consultants etc
|
Project Successes
|
Partnering
|
Whole Life Costs / Maintenance |
Unusual engineering techniques |
Client |
Environment Agency Contact Mr Scott Squires |
Value |
Award £ 1.4m Outturn £ 1.5m |
Role | Main Contractor |
Principal Designer |
Atkins Tel: 01792 641172 Contact: Mr Huw Richards |
Form of Contract | NEC Option C |
Contract Period | 26 weeks |
Dates | May 2006 to Nov 2006 |