Cynon River Emergency Works

A section of masonry river retaining wall, to the eastern edge of Riverside Park (Mountain Ash), on the western side of the Afon Cynon river channel, had collapsed into the watercourse. This resulted in a substantial void in the ground behind the collapsed area.

It was proposed that the existing collapsed section was to be removed and a blockstone revetment constructed in its place. The existing embankment was to be battered back to reduce the height of material retained and tied in horizontally to existing sound construction beyond the collapsed section.

Scope of the works

Site set up & erection of temporary works.

  • Site clearance & demolition existing unstable sections of retaining wall
  • Excavation for placement of blockstone
  • Construction of blockstone revetment, including placement of geotextile, fill and profiling of embankment.
  • Construction of re-aligned pedestrian footpath (including re-aligned guardrail)

The Emergency works were so successful that RCT had McCarthy’s back to undertake a further 3 phases over the following summers.

Client Organisation Rhondda Cynon Taff County Borough Council
Principal Contractor Centregreat
Contract Value £2,610,000
Role River Defence Subcontractors
Location 31 Cardiff Rd, Mountain Ash, CF45 4HA