Installation of blockstone scour protection to riverbank supplemented with erosion control matting to upper faces. All works undertaken in the river used a construction platform and silt control measures.
To gain access to the river and construct the works it was necessary to work within the rear gardens of 30 properties. At the end of the project the gardens were re-instated without complaint from the owners.
Additional works included the construction of 600m of reinforced concrete floodwall to the top of the bank. The flood wall passed through the rear of 2 businesses that had to be kept open throughout the duration of the works
The excellent liaison with the residents and businesses which were kept open for the duration of the works contributed to the scheme success. The project was completed on time with defences in place before the winter. The scheme was under PAR budget.
Value Engineering
|
Sustainability
|
Environmental
|
Partnering
|
Early Contractor Involvement
|
Risks |
Archaeology
|
Whole Life Costs / Maintenance |
Unusual engineering techniques
|
Involvement of other consultants etc
|
Client |
Environment Agency Contact: Mrs Suzanne Bland Tel: 029 2046 6000 |
Value |
Construction Award £ 2.65m Construction Outturn £ 2.7m Project Funding £ 4.5m Project Outturn £ 4.2m |
Role | Earthworks Contractor |
Principal Designer |
Halcrow Tel: 029 20720920 Contact: Mrs Sally Sudworth |
Principal Contractor |
Carillion Tel: 01656 767673 Contact: Mr Ian Thomas |
Form of Contract | NEC Option C |
Contract Period | 45 weeks |
Dates | May 2006 to March 2007 |