Problems overcome include: steep high batters made unstable due to groundwater; large flows of water and soft ground conditions.
As part of a works to construct housing, McCarthy's were employed to divert the River Ewelme and undertake drainage on the scheme.
Client Organisation | St Modwen |
Main Contractor | Hawk |
Contract Value | Circa £300,000 |
Contract Period | April - September 2016 |
Address | Lister Rd, Dursley, GL11 4BA |