The aim of the scheme is to reduce existing fluvial flood risk of the River Tawe to people and property within the lower reaches/downstream of the M4 motorway; comprising Swansea Vale, Swansea Enterprise Park, Riverside Caravan Park, Beauford Industrial Estate and the Plasmarl Industrial Estate.
Basic design to comply with the above was the construction/realigning of 6 number embankments in the various required locations.
Various Embankment's
As the main earthworks contractor on the site McCarthy's carried out all of the following activities for the embankment construction/realigning: -
Notes: See attached drawing for details of earthwork's quantities.
Construction of the attenuation area consisting of a number of settlement ponds with an outfall back to the river situated in front of embankment 5.
In addition to the above McCarthy's were given the following additional work whilst on site: -
Client | Natural Resources Wales |
Principal contractor | Galliford Try |
Main Contractor | McCarthy's |
Principal Designer | Black & Veatch |
Contract Period | 10 months |